Over the past 10 years Euro Demolition has been involved in hundreds of different demolition projects across Europe. Below, a representative selection of projects of the different demolition techniques employed is shown.
Chimney demolition
Demolition of the 150 meter high power plant chimney in Lelystad, Netherlands.
› view images
Hannover Messe
Precision demolition, 55 meter high building, demolition was a combination of high power cutting and lifting down upper parts of the structure.
› view images
Shell Pernis
Demolition of two aluminium silo's on Shell Oil plant, 78 meter high structures.
› view images
Krefeld bunker demolition
Demolition of the Krefeld bunker, 26 meter high, 2 meter thick walls, 50 Mt concrete, duration project three weeks.
› view images